gnezim 98c6eca90e Add Phase 6 cutover runbook and operational checklist
Comprehensive operational procedure for the Angular-to-React traffic
cutover: pre-cutover gates, proxy config templates (nginx/HAProxy),
72-hour traffic ramp schedule, monitoring checklist, rollback procedure,
1-week soak criteria, and Angular decommission steps. Also adds Phase 6
cross-reference sections to the Phase 1 runbook.